Around 9am- Lu and Jonny showed up and it was us 3 for a good while.... we managed to level the ground on the south and east face, lay tires down and pounded a few.

I'd say it was around 11am that more folks started to show up, 3-4 people now bucket running and pounding tires.
The sun did a good job at staying just on the edge of the clouds and gave us enough warmth.
Around 1 o clock, we decided to light the fire for it was getting colder, more people showed up to help, maybe 4 more.

From 1-3:15 or so, Roughly 10 of us were pounding tires, bucket running, and tending the fire to stay warm.
3:15pm - Clean up was called.
The rest of the time until a little past 4 was spent brainstorming on how to attract more people for next week.
Sidenote- Tires were on site already, but once some people saw what we were doing....people brought us tires.